Nereda design capacity

  • 1422 m3/d
    Dry Weather Flow
  • 59 m3/h
    Peak Flow
  • 32942 PE
    PE (PE = 60 gBOD/d)

Project facts

  • Client
    Westfort Meatproducts
  • Location
    IJsselstein, The Netherlands
  • Period
    2015
  • Wastewater
    Industrial
  • Project type
    Greenfield

About the Nereda® WWTP at Westfort

Nereda was selected by Netherlands-based Westfort Meatproducts for one of the world’s most innovative, sustainable and animal welfare respecting pig slaughterhouses. With its small footprint, sustainability, low energy use and robustness the Nereda technology fits perfectly with the needs of Westfort. Royal HaskoningDHV was responsible for detail engineering, delivery, installation and start-up of the Nereda wastewater treatment installation, Promad for civil engineering and project management and RWB built the installation.

The Nereda technology was implemented in two rectangular, completely covered concrete tanks, with a technical area on top of the tanks and a parking deck at the roof of this technical area. The work was completed mid-November 2015. Because Westfort immediately needed a good effluent quality granular sludge of the Nereda installation in Garmerwolde and of the pilot plant in Utrecht was used for the start-up. This approach seemed successful in the first week. Royal HaskoningDHV is following the treatment process real time by using a tailor made AquaSuite® Nereda Controller.